2023 - Street Thin Overlays

Project Type:
Street
Project Status: 
Approved and Under Construction

Crews will be doing preparation and thin overlays throughout the City the week of September 18, 2023.

No Parking signs have been posted for Monday, September 18 for prep work and Thursday, September 21 and Friday, September 22 for paving of thin overlays.

Streets affected:
Josephs Court  (from West Golf to Cul-De-Sac)
Grandview Lane  (from Eighth Avenue to Dead End)
Gridley Avenue  (from S. Court Street to Dead End)
Jewett Street  (from Lancaster Street to Hickory Street)
Colleen Court  (from Hollman Street to Cul-De-Sac)
Williams Street  (from Hollman Street to Hathaway Street)
Carlisle Street  (from Rountree Avenue to Court Street)
North Street  (from E. Mineral Street to Dead End)
Dewey Street  (from Seventh Avenue to Lancaster Street)

Please note: The 2022 overlay (highlighted in green) is also included – Second Street from Pitt Street to north City Limits.

2023 Thin Overlay map
Status Updates

September 27, 2023
Thin Overlay streets have all been completed.

September 20, 2023
Thin Overlay streets will be paved on Thursday/Friday this week.