New Platteville Fire Facility Project

Fire Facility Progress Photos 7-18-25

Welcome to the New Platteville Fire Station Project page.  Here you can find useful information regarding the process of building the new Fire Station, links to presentations, fundraising information and donor recognition.

Progress Update 7/14/2025

  • Utilities work is nearly complete except for a small section of storm sewer and the main electrical work which will come in after footings and foundations are set. Rain has delayed progress by at least a week, but crews are working diligently to catch up.
  • During the week of July 14, the focus will remain on foundations and footings. Footings were initially scheduled for 6 weeks and foundations for 9 weeks, with backfilling to follow. Metal framing could start as early as August 4, if crews are able to catch up.
  • Staff continue to work with Wendel and Kraemer on a solution for the elevation of the Court Street sidewalk. Elevations in the 3-D rendering did not accurately depict the intersection of Court Street and Adams Street (high point of the parcel) in comparison to the fire facility parking lot.